Two 500-ton crawler cranes completed the hoisting of the feed heat exchanger of the Qingyang Petrochemical Project Department.Turkey Excavator sprocket

Two 500-ton crawler cranes completed the hoisting of the feed heat exchanger of the Qingyang Petrochemical Project Department.Turkey Excavator sprocket

IMGP1826

On June 21, the Qingyang Petrochemical Project Department of PetroChina Sixth Construction Co., Ltd. operated two 500-ton crawler cranes to complete the largest hoisting operation on the construction site—the hoisting of the 115-ton E-201 feed heat exchanger.Turkey Excavator sprocket

Since the demolition and operation of the second second reactor on the 17th, the project department has attached great importance to the hoisting task of the 500-ton crawler crane. While not affecting the construction plan of other areas, it has coordinated with various departments to ensure the hoisting of the 500-ton crawler crane. The operation was carried out smoothly, and the disassembly and loading of the reactor, upper hopper, platform frame, elbow flange, economizer induced draft fan, heat exchanger and other components of the reforming unit were completed successively.Turkey Excavator sprocket

On the 21st, under the condition of sufficient preparation conditions, at 10:15, the project department held a brief safety technical briefing for the operators involved in the hoisting of the E-201 feed heat exchanger, from the hoisting route to the site safety. Management, the precautions in the hoisting process and the specifications of the equipment were explained one by one. At 10:30, the hoisting operation of the E-201 feed heat exchanger officially started. At 11:30, the E-201 entered The material heat exchanger was hoisted into the platform frame and the installation was completed. So far, the 500-ton crawler crane has completed the hoisting operation of the largest and heaviest piece of equipment on the construction site.Turkey Excavator sprocket

Since the overhaul, all departments of the project department have worked together to keep abreast of the construction progress. All work is carried out around the smooth delivery of the overhaul. There are a total of 640 overhaul projects, 511 of which are in progress, and the overall progress of the overhaul has reached 21%. Orderly.Turkey Excavator sprocket

 